BULK PRODUCTIONG
The following are all the steps of our bulk production and the days needed for each step, for your reference, so that we can push the bulk production can proceed smoothly. Fabric prepare (10~13 days) ----- Print or dye fabric (5~6 days) ----- Order tech pack (1~2 days)-----Tailor(3~5days)-----embroidery(3~5 days)----- Sewing(3~10 days) ---- Trimming (3~4 days) ----- Ironing (3~4 days) -- --- Examine(1~2 days)----- Packing(3~4 days)----- Needle inspectio n (1~2 days)----- Binning(1~2 days)----- Goods inspection (1~3 days)----- shipping ----- Total 40~45days